sector guide · Construction Ledger

Running a build

A house or a small block put up for owners who are often abroad, by a contractor or by a relative who buys the materials and pays a fundi. For the Board that contracts and pays, the site's people who record on their phones, and the engineer who certifies the work.

Tabs
Building, Stock, Money, Approvals, Governance, and what every holding has
Roles
Board, Manager (the office), Worker (the site), Engineer, Counter
Phones
Hold-point photos, snags, materials issued to a stage, deliveries and the site's count
The balance
A contractor is never paid more than the work certified, less retention, plus advances not yet recovered
Verifier
ledger-verify --building

Watch it working

Short films of each step on a build set up for demonstration, with its people and figures made up. Each opens in a new tab.

  1. The Board sets up the buildThe contract, stages and plot; a stage past the contract sum refused; an advance over the cap refused, then agreed.
  2. Who does what on a buildThe engineer sees the build but no money; the office cannot contract or certify; the Board cannot be its own engineer.
  3. The site worker's phoneCement delivered and issued, an over-plan issue raising an exception, a hold-point photo and one outside the plot.
  4. The engineer certifies the workA certificate refused without a photo; one made with retention and advance recovered; past the budget refused.
  5. Variations and signed dayworksVariations ordered, priced and approved; the variations limit raised and cleared; dayworks signed.
  6. Paying the contractorA remittance in, the advance paid, and an interim payment past what is payable raising an exception.
  7. Closing the build's monthThe close refused while the contractor is overpaid; the payment reversed; the month closed; the store counted.
  8. Reports, the bundle and the verifierThe build in the flash and both packs, and the bundle with its photos checked by ledger-verify --building.
  9. The console, read for a buildPeople, Approvals, Money, Periods, the build's settings, Plan, Help and the build's own guides.
  10. The build's calendarStages given their dates; one past its finish shown late and raised to the Board; its finish moved with a reason, the first date kept beside it.
  11. The cash-flow forecastThe stages' budgets by month from their dates, beside what was certified and paid, against the sanction; stages with no dates shown apart; never for the engineer.
  12. Snags, cleared on siteTwo snags recorded with photos on the site phone; one cleared on a new photo taken on site; the other withdrawn by the Board with its reason.
  13. An independent count of the storeThe site worker refused as counter; a counter appointed counts blind and finds five bags short; only the Board writes them off, and the exception resolves.

The build, and who does what

A build is cheated in two usual ways: work covered up before anyone saw it, and money paid for work not done. The Construction module keeps three people apart so that no one can do both. The Board contracts, plans and approves payments; the office records the payments; the engineer certifies the work and never records a payment.

WhoWhat they record
BoardContracts, stages, advances, variations ordered and approved, and the approval of every payment.
Manager (the office)Payments and receipts in Money; on the phone, the same site work as a worker.
Worker (the site)On the phone: hold-point photos, materials issued to a stage, deliveries to the site store and the store's monthly count.
EngineerOn the phone, their own hold-point photos and snags; in the console, variations priced, daily sheets signed and certificates. See Engineer.
CounterOn the phone, the site store's count and nothing else, once the Board appoints one. See Counter.

The engineer is someone the Board adds in People with the role Engineer: a registered engineer, architect or quantity surveyor. An engineer who is also on the Board, the forum or a manager of the build certifies nothing, and nor does one with a declared interest in the contractor. The engineer sees the Building tab and nothing of the money.

Setting it up (the Board)

  1. Set the build's currency in Settings (money.currency).
  2. Sanction the build as a capital project on Governance. Its amount is what the funders agreed to; the contracts never add up to more.
  3. Under Places on the Building tab, define the site and outline it on the map, then add a store under it for the materials. A photo of the work counts only if it was taken inside the outline.
  4. Add the contractor, or the fundi, to the register in Money as a supplier.
  5. On Stock, add the key materials as Building material: cement, blocks or bricks, steel by bar size, iron sheets, timber, sand and aggregate.
  6. Add the site's people and the engineer in People, and enrol their phones (see People, access and phones).

Contracts

  1. Under Record a contract, choose Who builds: a contractor with their own labour and materials, or a fundi paid for labour only while the owner buys the materials.
  2. Choose the contractor or fundi, the capital project, the site and the contract sum. The project shows what is not yet contracted.
  3. Set the retention and the defects period. The Board's settings suggest them: 5% and 12 months unless it has changed them.
  4. Press Record the contract.

Once recorded, a contract's sum, retention and defects period stay as they are. A change of price or scope is a variation.

Stages and the bill of quantities

Each contract is planned in stages, in order. A hold point is work that the next stage covers up: it is photographed before it is covered, because that is where a build is cheated. Plan a stage offers the usual stages, which you may rename or add to.

Usual stageHold point
Site clearance and setting outPegs and profiles against the approved plan
Foundations to DPC and slabTrench depth with a tape in shot; reinforcement before the pour
Walling to ring beamRing-beam steel before the pour
Roof structure and coveringTrusses and fixings before the sheets
Lock-up (windows, doors)None
Services first fixConduits and pipes before plaster
Plaster, screed, finishesNone
External worksNone
Practical completionThe whole building
End of the defects periodThe defects list closed
  1. Under Plan a stage, start from a usual stage or name your own, and give its order.
  2. Give its budget. Or, for a contractor-built project with a full bill of quantities, paste its lines (description, unit, quantity, rate, one line each) or read them from a CSV file: the budget is then the bill's total.
  3. Give its hold point, if it has one.
  4. Add the key materials it is expected to use, and how much of each, then press Plan the stage.
  • The stages of a contract never come to more than its sum.
  • A stage can be retired until its work is certified; after that its budget may still change, never below what is certified. A stage with certified work stays in the work.

Advances

A mobilisation advance is agreed under Agree an advance, within the Board's cap: 15% of the contract unless it has changed it. The form shows what is left under the cap. The advance is paid in Money like any payment, and recovered from later certificates.

Dates and the cash-flow forecast

  1. Under Schedule a stage, the Board gives a stage the day it starts and the day it finishes, and presses Save the dates. The stage list shows them under Planned dates.
  2. Moving the dates needs a reason, and every change stays listed beside the first dates. A finished stage's finish is never moved.
  • A stage is finished when its certificates reach its budget, or when its contract is certified practically complete, whichever comes first. One not finished more than the Board's grace (7 days unless it has changed it) after its planned finish is late, and the Board is told until it finishes or its dates are moved.
  • Cash-flow forecast, on the Contracts tab, spreads each scheduled stage's budget over its planned days, month by month, beside the work certified and what the contractors were paid, each also to date, against the capital project's sanction. Stages with no dates are counted apart, never guessed. The engineer does not see it.
  • The flash, the pack and the investor pack add what was planned to be certified by their day, and how many stages are late.

On site: photos and materials

The site's phones open on On site with the contract's stages. Each record goes to the office at the next sync.

Photograph a hold point

  1. Choose the stage. Its hold point says what to photograph.
  2. Stand on site and take the photo, close enough to see the work, with a tape in shot where depth or size matters.
  3. Add a note if it helps, and press Save. One photo is one record: take each further photo the same way.

The phone writes where the photo was taken into the photo itself, from its GPS. In the console each stage lists its Hold-point photos: on site means inside the site's outline, outside the site means not, and no place means the phone had no GPS fix. Only photos taken on site, before the next stage's work started, count towards certifying a stage.

Materials

  • Deliveries to the site store are recorded on the phone as they arrive, as in any store (see The stock ledger).
  • Issue material records material taken from the store for a stage: choose the stage, the material and how much. The phone shows what the store holds and what the stage has used of its plan, and refuses taking more than the store holds by the record: record the delivery first.
  • Using more than the stage planned is saved. Beyond the Board's margin (10% unless it has changed it), the phone says so and the Board is told.
  • The site store is counted from the phone each month. What was bought must equal what was issued to a stage, counted on site, or written off or found by the Board with a reason.
  • Once the Board appoints a counter (see Counter), only the counter counts the store, and is never one of those who issue from it. With none, the site's people count it, and the Building tab says the count is not independent.
  • A building material leaves the store only issued to a stage, or by the Board under Write off or find a material, with its reason and a note. Of the store's records, a phone makes only a delivery, an issue to a stage and a count of a material: never a loss, a use or a move. A material stays a material: its kind is never changed.

An engineer's phone records only hold-point photos and snags. What moves in the store is the site's people's to record.

Snags

A snag is a defect the contractor must put right. The defects list is kept on the record, each snag with its photo.

  1. On the phone, under Snags, press Record a snag: choose the contract and, where it is one stage's work, the stage; say what is wrong; take the photo; press Save. A snag is kept wherever its photo was taken, so none is lost; the console shows whether it was taken on site.
  2. Once it is put right, press Clear a snag, choose it and photograph the work on site. A clearance on a photo taken anywhere else, or with no place, is refused.
  3. A snag recorded in error is withdrawn by the Board on the Building tab under Withdraw, with its reason. A withdrawal cannot be undone: a defect found again is a new snag.

The final certificate is refused while any snag on its contract is open. Practical completion is never held by them.

Variations and dayworks

A change of scope or price is a variation, ordered before the work. Work beyond a stage's budget without an approved variation is never certified, so never paid.

  1. The Board presses Order a variation, names the stage and says whether it is paid as a lump sum or as dayworks, against signed daily sheets.
  2. The engineer presses Price it. For dayworks, the price is the most the daily sheets may come to.
  3. The Board presses Approve. Approval is final, and must stay within the capital project's sanction and tolerance; beyond that, the Board varies the project on Governance first. Nothing more is committed to a closed project.
  4. For dayworks, the engineer presses Sign a daily sheet for each day's work. Only signed sheets count, up to the price, and a signature cannot be taken back.

The heading Variations shows what share of the contract has been approved. Past the Board's alert share (10% unless it has changed it), the Board is told.

Certificates (the engineer)

  1. Under Make a certificate, enter what each stage's work done since the last certificate is worth. Each stage shows what is left to certify.
  2. Enter any advance recovered, then read the preview: worth, retention held, retention released, payable.
  3. Press Make the certificate and confirm. A certificate cannot be changed or withdrawn: a correction is a later certificate.

The app refuses a certificate when:

  • the engineer has no photo of their own of the stage taken on site;
  • the stage has a hold point and no photo of it was taken on site before the next stage's first record;
  • the stage would be certified past its budget and approved variations;
  • it recovers more of an advance than is still to recover, or than the certificate leaves payable.

Each certificate holds back the contract's retention. A Practical completion certificate, made once, releases half the retention held. The Final certificate follows practical completion, once the defects period has run and with no snag open, and releases the rest. After it, nothing more is certified.

Paying the contractor

  • The office records each payment in Money, naming the contractor, and the Board approves it as any payment (see Approvals, sales and the governance pack). Retention released is paid the same way.
  • The Building tab shows each contract's position: certified, retention held, advance still to recover, payable to date, and what has been paid.
  • A contractor is never paid more than the certificates leave payable plus the advances agreed. A payment past that is raised to the Board and holds the month open until a certificate or a reversal brings it back.
  • A fundi on a labour-only contract is certified and paid under the same balance; the materials the owner buys go through the site store.

Exceptions

Besides the exceptions every holding has (see Exceptions and escalation), a build raises these of its own, to the Board unless it says otherwise.

ExceptionWhenWhat to do
Stage using more material than plannedMaterial issued to a stage is past the Board's margin over its planAsk the site why. It never stops the work or the month.
Variations past the alert share of a contractApproved variations are past the Board's alert share of the contract sumExplain the growth to the funders, or vary the project on Governance.
Contractor paid more than certifiedA contractor's payments are past what the certificates and advances leave payableHave the engineer certify the work, or reverse the payment in Money.
Stage not finished by its planned finishA scheduled stage is not finished more than the Board's grace after its planned finishFind out why, then move its dates with the reason, or press the contractor.
Hold point waiting for a certificateA hold point photographed has waited the Board's days with no certificate (the manager's; the engineer is emailed once)Ask the engineer to inspect and certify before the next stage covers it.
Defects period endingA contract's defects period ends within the Board's notice (30 days unless it has changed it), with its snags still openWalk the site with the engineer and record every snag before it ends.
Retention due after the defects periodThe defects period has ended and retention is still held, with its snags still openHave the snags cleared, then the engineer makes the final certificate.

The staff: checks, training, absence and leave

  1. On the Staff tab, the Board names what the staff must hold: each check or course, how often it is renewed, what it is needed for and, if not everyone, the roles it applies to. A starting list is offered: site induction, working at height, a trade certificate for skilled trades.
  2. The manager opens a person's row and records each check or course: the day, its expiry if it states one, its number and who gave it.
  3. Nobody is booked here, so nothing is refused: the table and the exceptions follow each person. What a check says (its number and who gave it) is kept off the chain, the chain holding its fingerprint; keep the certificate on paper.
  4. The manager is told of each check or course expiring within 30 days, lapsed or missing.
  5. The Board sets the holiday year (weeks a year, or days for each month worked) and each person's working pattern. Each absence is recorded with its days and why; why is never written on the chain. Annual leave says what it takes, and the table shows what each person is entitled to, has taken and has left.
  6. After sickness the manager records the return to work. The Board is told of leave over the entitlement; the manager, of a pattern of sickness and of a return to work not yet held.

Closing the month

A build's month closes as any holding's does (see Closing the month), with its cash and bank counted and agreed, and only when:

  1. no contractor is paid past what the certificates and advances leave payable, and
  2. every store that holds building materials has been counted on site for the month, from the phone.

Reports, the bundle and the verifier

  • The weekly flash, the monthly pack and the investor pack carry the build in one line: the contracts and their sum, certified, paid, retention held, advances to recover, variations approved and the stages certified.
  • Download the verification bundle, on the Building tab, gives every record, every hold point's photo and every snag's. It is for the Board, the manager, the forum and the auditor, not the engineer.
  • Anyone holding it runs ledger-verify --building on it. The tool works each certificate out again, checks each photo was taken inside the site, and compares what each contractor was paid with what the certificates leave payable. It also replays the planned dates and the stages late, refuses a final certificate made over an open snag, and replays the store's ledger, its counts and the materials used past each stage's plan. See Checking the records.

The build's own settings

These settings are a building's alone, set by the Board in Settings. The starting figures are common practice, still to be confirmed by a quantity surveyor for Uganda.

SettingStarts atWhat it does
building.retention_pct5 (0 to 10)Retention a new contract holds back from each certificate, per cent
building.defects_months12 (3 to 24)Months after practical completion that a new contract's defects period runs
building.advance_cap_pct15 (0 to 30)The most a contractor may be advanced, per cent of the contract sum
building.material_tolerance_pct10 (0 to 50)How far a stage may use more of a key material than planned before it is an exception
building.variation_alert_pct10 (0 to 50)Variations beyond this share of a contract are raised to the Board
building.late_grace_days7 (0 to 60)Days after its planned finish before a stage not finished is late
building.holdpoint_days7 (1 to 60)Days a hold point photographed may wait for a certificate before the manager is told
building.defects_notice_days30 (7 to 90)Days before the defects period ends that the Board is told

The Board may switch the materials' ledger off in Settings (building.features) for a build that keeps none; its money is always on. Pro's price for a build is set by what its contracts come to (see Plans, and creating a ledger yourself).